Match The Following
Question  -- Correct Answer  --  Your Answer
Secondary Process -- Maintenance -- Maintenance
Knowledge Process  -- Research & Development -- Research & Development
Key Process -- Process supporting the mission of company -- Process supporting the mission of company
Operational Process -- Manufacturing -- Manufacturing

Select The Blank
Question RFP is ________.
Correct Answer Request For Proposal
Your Answer Request For Proposal

Multiple Choice Single Answer
Question Prioritization of customer requirement is done through :-
Correct Answer Customer's interview
Your Answer Customer's feedback

Select The Blank
Question ________ is the starting point for process reengineering efforts.
Correct Answer Customer identification
Your Answer Customer identification

True/False
Question Organization has both internal & external customers.
Correct Answer True
Your Answer True

Match The Following
Question -- Correct Answer -- Your Answer
ERP Challenge 4 -- Organizational Intervention -- Organizational Intervention
ERP Challenge 1 -- Change Management -- Change Management
ERP Challenge 2 -- Shifting from Function to Process View -- Shifting from Function to Process View
ERP Challenge 3 -- Faith in Package Software -- Faith in Package Software


True/False
Question The introduction of a new information technology often changes the complex power structure in an organization.
Correct Answer True
Your Answer True

True/False
Question A business process is defined as "a set of logically related tasks performed to achieve a desired business outcome".
Correct Answer True
Your Answer True

Multiple Choice Single Answer
Question Activities performed by middle management is :-
Correct Answer Strategic activities
Your Answer Tactical activities

Select The Blank
Question Breakthrough Results in search for & the implementation of radical change in business process are by ________.
Correct Answer BPR
Your Answer BPR

Multiple Choice Multiple Answer
Question Integration Strategy is related to :-
Correct Answer Information Integration , Decision Integration , Financial Integration
Your Answer Information Integration , Decision Integration , Financial Integration

Multiple Choice Multiple Answer
Question IT applications to improve business process are :-
Correct Answer In supporting product development process , In supporting order fulfillment process , In supporting logistical process
Your Answer In supporting logistical process , In supporting product development process , In supporting order fulfillment process

Select The Blank
Question Simplification & Re-engineering can overlap together from the ________ of an organization.
Correct Answer Process Orientation
Your Answer Process Formation

Select The Blank
Question ________ weigh the efficiency and productivity by characteristics of a process.
Correct Answer PCM
Your Answer CTS

Multiple Choice Multiple Answer
Question Guidelines for Business transformation are :-
Correct Answer Map the current state of the organization & its business processes , Chart out the desired goals , Develop high level process specifications
Your Answer Map the current state of the organization & its business processes , Chart out the desired goals , Develop high level process specifications

True/False
Question Work should be broadened without sacrificing depth of expertise in strategic areas.
Correct Answer False
Your Answer True

Multiple Choice Multiple Answer
Question MRP II is associated with :-
Correct Answer Men , Machine , Material
Your Answer Men , Machine , Material

Multiple Choice Single Answer
Question Strategic planning system if for the :-
Correct Answer Future prediction situation
Your Answer Future prediction situation

Multiple Choice Single Answer
Question Micro level reengineering deals in relation to time frame which is :-
Correct Answer Short
Your Answer Medium

Select The Blank
Question Cycle Time, Asset Turnover & Response Time goals are achieved by ________.
Correct Answer Velocity Goal
Your Answer Productivity Goal

Multiple Choice Single Answer
Question Kaizen means :-
Correct Answer Continuous Improvement
Your Answer Continuous Improvement

Select The Blank
Question Breakthrough Results in search for & the implementation of radical change in business process are by ________.
Correct Answer BPR
Your Answer BPR

Multiple Choice Single Answer
Question Tactical systems maintains information :-
Correct Answer In the form summary of data
Your Answer In the form summary of data

Multiple Choice Multiple Answer
Question The Top Management should also ensure the support of :-
Correct Answer Senior Managers , Stakeholders , Associates
Your Answer Senior Managers , Associates , Processes

Multiple Choice Multiple Answer
Question Benefit paths of process re-engineering in an organization are :-
Correct Answer Productivity , Quality , Velocity
Your Answer Productivity , Quality , Finance

Select The Blank
Question ________ BPR methodology has a source as "Consultant".
Correct Answer Manganelli/Klein
Your Answer Manganelli/Klein

Multiple Choice Multiple Answer
Question Application Systems Languages are :-
Correct Answer ABAP/4 , VB , VC++
Your Answer VB , VC++ , ABAP/4

Multiple Choice Multiple Answer
Question Critical Success factor in business are :-
Correct Answer Cost reduction , Quality enhancement , Service improvement
Your Answer Cost reduction , Quality enhancement , Service improvement

Multiple Choice Single Answer
Question Process orientation means :-
Correct Answer Organizing companies around their processes
Your Answer Organizing companies around their processes

Multiple Choice Single Answer
Question The BPR activities are used in conjunction with :-
Correct Answer Workflow Analysis
Your Answer Workflow

True/False
Question A vision statement defines the future direction of the organization.
Correct Answer True
Your Answer True

True/False
Question Success factor for BPR is a proper composition of re-engineering team with in-depth knowledge of the topic.
Correct Answer True
Your Answer True

Select The Blank
Question In Kaizen, focus is on ________ Improvement.
Correct Answer Continuous
Your Answer Continuous

Multiple Choice Multiple Answer
Question Which of the following are the derivatives of business system planning methodology?
Correct Answer Information system planning , Information requirement study
Your Answer Information system planning , continuous improvement system , Time & motion study

True/False
Question ERP software must not address all the enterprise needs of an organizational within the social context in which the enterprise operates.
Correct Answer False
Your Answer False

Select The Blank
Question ________ are those things that the organization does best.
Correct Answer Core competencies
Your Answer Business process

Multiple Choice Multiple Answer
Question ERP can be made effective by :-
Correct Answer Performance assessment , Documentation , Training
Your Answer Performance assessment , Documentation , Training

Multiple Choice Multiple Answer
Question Areas of Productivity Increase are :-
Correct Answer Quality , Quantity , Rejection Level
Your Answer Quality , IT , Rejection Level

Multiple Choice Multiple Answer
Question Integration of re-engineering & process improvement activities is done by :-
Correct Answer Sequencing change initiatives , Limiting the scope of work design , Undertaking improvement through innovation
Your Answer Sequencing change initiatives , Undertaking improvement through innovation